Lesson
Ensure that Highway Patrol's CAD system operators enter key information needed by the transportation management center operators.
Experience from iFlorida Model Deployment
01/30/2009
Florida,United States
Background (Show)
Lesson Learned
The primary objectives of the various Florida Department of Transportation (FDOT) interfaces to the Florida Highway Patrol Computer Aided Dispatch (FHP CAD) system were to provide the FDOT Regional Traffic Management Center (RTMC) operators with an improved source of FHP incident information, which they could use to support the Central Florida and Statewide 511 systems. The first version of this interface was not very successful, and many operators preferred to refer to the incident information available via the FHP Traffic Crash Reporting Web site rather than rely on the CRS to provide incident information. The second version of this interface (the FHP Data Viewer), however, was successful.
While deploying and operating these systems, FDOT did identify a number of lessons learned that other locales may find useful.
While deploying and operating these systems, FDOT did identify a number of lessons learned that other locales may find useful.
- Work with the Highway Patrol to ensure that practices are in place to enter key information needed by the DOT in the correct fields within the CAD system. The data needs of FHP were different from those of FDOT, so some data fields that were key to FDOT but not key to FHP were not always entered consistently. One example was the road name, which was sometimes entered in the FHP CAD system as part of the free text description rather than in the road name field. FHP cooperated closely with FDOT by encouraging its dispatchers to follow more stringent data entry requirements with respect to these fields.
- Provide mechanism to translate data from the FHP CAD system to values recognized by FDOT. An example was the incident type. Because FHP sometimes revised the list of acceptable values for incident types and their meanings, FHP instituted procedures to ensure that the tables used to translate FHP incident type values to FDOT values would be updated whenever such changes occurred.
- Implement methods to identify and recover dropped messages in case of event-driven messaging. A system that uses event-driven messaging should include methods for identifying and recovering from dropped messages.
Lesson Categories
States
Countries
Systems Engineering
Show the V
Software / Hardware Development Field Installation
Focus Areas
None defined
Goal Areas
Keywords
None defined
Lesson ID: 2009-00493

Lesson Comments
No comments posted to date