Unit Cost Entry

Unit Cost Element - Roadside Signal Preemption/Priority

Unit Cost Component - Roadside Signal Preemption/Priority


Atlanta, Georgia, USA


Description

3M - Opticom Detector, Phase Selector, and System Software. Capital costs are for two directions and include installation costs. O&M costs include man-hours for monitoring system settings, in addition to field maintenance. Replacement costs are not included.

Cost Type

Estimated

Data Date

2005

Reported Units



Units

Each (EA)

Year (Dollars)

2005

Capital Cost per Unit ($)

$5,600.00

O & M Cost per Unit ($)

$1,100.00

Lifetime

10 years


Notes

*2005*. Unit Measurement Details: Per Intersection

Source

ITS Integration Program Unit Cost Data Collection Sheet: Atlanta Smart Corridor - Atlanta, GA (FY2 Yr3)

Author: Valentin Vulov


Unit Cost Details

Capital Cost per Unit: $5,600.00

O&M Cost per Unit: $1,100.00

Year (Dollars): 2005

Lifetime: 10 years