Unit Costs (Adjusted) (View Unadjusted)

Equipment Costs for Roadside Control (RS-C)

Note: Equipment list adjusted to 2008 dollars. The date in parentheses under the capital cost value and O&M cost value represents the dollar year from which the cost value was adjusted. All costs are in $K.

Unit Cost Element IDAS # Life
Years
Capital Cost
$K, 2008 Dollars
(Source Year)
O&M Cost
$K/year, Dollars
(Source Year)
Description
Linked Signal System LAN
Index: 2
RS0022020.0 - 48.0
(2005)
0.3 - 0.5
(1995)
This element provides the connections to the linked signal system.
Signal Controller Upgrade for Signal Control
Index: 2
RS003202.1 - 5.0
(2003)
0.2 - 0.4
(2005)
Local controller upgrade to provide advanced signal control.
Signal Controller and Cabinet
Index: 2
7.0 - 12.0
(2005)
0.2 - 0.4
(2005)
Includes installation of traffic signal controller per intersection.
Traffic Signal
Index: 2
78.0 - 94.0
(2001)
1.9 - 2.4
(1999)
Includes installation for one signal (four-leg intersection), conduit, controller, and detection device. Cost ranges from traffic signal with inductive loop detection (low) to non-intrusive detection (high).
Signal Preemption Receiver
Index: 2
RS00452.0 - 5.0
(2004)
0.03 - 0.20
(2004)
Two per intersection. Complement of IDAS elements RS005 and TV004.
Signal Controller Upgrade for Signal Preemption
Index: 2
RS005102.0 - 4.0
(2005)
Add-on to base capability (per intersection). Complement of IDAS elements RS004 and TV004.
Roadside Signal Preemption/Priority
Index: 2
104.0 - 5.0
(2005)
0.2 - 1.0
(2005)
Includes infrared detector, detector cable, phase selector, system software, and installation. Capital costs range is for two-directions. O&M cost estimate for operating, monitoring, and maintaining. Complement to transit (or emergency vehicle) on-board Signal Preemption/Priority Emitter. Capital costs can exceed $20K to $30K per intersection if traffic control equipment and/or systems need to be replaced.
Ramp Meter
Index: 2
RS006521.0 - 42.0
(2003)
1.0 - 2.4
(2003)
Includes ramp meter assembly, signal displays, controller, cabinet, detection, and optimization.
Software for Lane Control
Index: 3
RS0112025.0 - 50.0
(1995)
2.0 - 5.0
(1995)
Software and hardware at site. Software is off-the-shelf technology and unit price does not reflect product development.
Lane Control Gates
Index: 2
RS0122068.0 - 102.0
(1995)
1.4 - 2.0
(1995)
Per location.
Fixed Lane Signal
Index: 2
RS009204.0 - 5.0
(1995)
0.4 - 0.5
(1995)
Cost per signal.
Automatic Anti-icing System - Short Span
Index: 2
1219.0
(1998)
1.5
(1998)
Typical automatic anti-icing system consists of a control system, chemical storage tank, distribution lines, pump, and nozzles. Pump and control hardware replaced every five years. For a short span system ranging from 120 to 180 feet. O&M includes system maintenance, utilities, materials, and labor.
Automatic Anti-icing System - Long Span
Index: 2
1239.0 - 388.0
(1999)
1.2 - 23.1
(1999)
Typical automatic anti-icing system consists of a control system, chemical storage tank, distribution lines, pump, and nozzles. Pump and control hardware replaced every 5 years. For a long span system ranging from 320 feet to greater than 1/2 mile. O&M includes system maintenance, utilities, materials, and labor. The high O&M cost is for a much larger system; hence, the need for a greater amount of materials.