The I-25 Truck Safety Improvements Project
Statewide, Colorado, United States
In 1998, the Congress designated the I-25 Truck Safety Improvements Project (I-25 TSIP) to support transportation improvements in the State of Colorado. This project was intended to improve transportation efficiency, promote safety, reduce emissions, improve traveler information, enhance alternate transportation modes, promote tourism and build on existing Intelligent Transportation Systems (ITS).
Total funding for the I-25 Truck Safety Improvements Project is $11,250,000. Of the total, $9,000,000 are federal funds (80%) and $2,250,000 are matching state funds (20%). The project was divided into tasks to address the ITS needs of the Colorado Department of Transportation (CDOT) in areas ranging from planning through detailed design and implementation. Project tasks and accompanying costs are listed in the following table.
Task
|
Costs
|
I-25 Truck Safety Reimbursement, Region 1 |
$1,200,000
|
Install AVI/WIM, I-25 Monument |
$414,258
|
Enhance Web for CVO data. Install POE Computers |
$48,000
|
Install AVI/WIM, I-25 Fort Collins |
$480,538
|
Install AVI/WIM, I-70 Limon |
$407,453
|
CTMC Operations |
$681,964
|
ATMS/ATIS – Communications |
$60,000
|
ATMS/ATIS – NTCIP DMS Driver |
$57,000
|
ATMS/ATIS – Web Integration |
$449,751
|
ATMS/ATIS – Denver Fiber Ring |
$454,268
|
ATMS/ATIS Integration – Miscellaneous |
$210,640
|
I-25 Interconnect, CTMC – Colorado Springs |
$627,000
|
I-25 HAR, Region 4 |
$56,596
|
I-25 DMS, Colorado Springs |
$1,190,496
|
I-25 DMS, Region 4 |
$750,000
|
I-25 ATR/WIM, Region 4 |
$84,417
|
1-800 Road Weather Information Line |
$150,000
|
I-70 Hanging Lake Tunnel Integration |
$288,000
|
Denver Area Speed Map |
$200,000
|
I-25 Stadium Parking Management., Denver |
$300,000
|
Develop C2C interface with City of Lakewood |
$250,000
|
Message Paging Interface |
$150,000
|
CCTV for Regions 1 and 6 |
$500,000
|
Colorado Springs Area Speed Map |
$200,000
|
Statewide Speed Map |
$200,000
|
Weather Systems Integration |
$100,000
|
Low-Speed Communications |
$820,599
|
Traveler Information Center (TIC) |
$400,000
|
Public Information & Incentive Leverage |
$14,130
|
Transit Data Integration / Kiosks |
$100,000
|
Start-Up Tasks |
$354,890
|
TOTAL |
$11,250,000
|
I-25 Truck Safety Improvements Project Local Evaluation Report
I-25 Truck Safety Improvements Project - $11,250,000.