Identifier Cost Subsystem Unit Cost Element Unit Cost Component Description Capital Cost Per Unit OM Cost Per Unit Adjusted Capital Cost Per Unit Adjusted O&M Cost Per Unit Reported Units Lifetime Location Unit Cost Type Unit CPI ID CPI Name Year Source Associated System Cost
UC2011-01531 Roadside Telecommunications (RS-TC) Conduit Design and Installation - Corridor Conduit 1 - 50 mm (2 in.), Trenched

furnish and install conduit

$9.75 $11.03 Topeka, Kansas, United States Actual Linear Foot (LF) 1 WPU1176 "KDOT Unit Costs 2009.pdf" -…
UC2011-01532 Roadside Telecommunications (RS-TC) Conduit Design and Installation - Corridor Conduit 1 - 75 mm (3 in.), Trenched

furnish and install conduit

$11.28 $12.76 Topeka, Kansas, United States Actual Linear Foot (LF) 1 WPU1176 "KDOT Unit Costs 2009.pdf" -…
UC2011-01533 Roadside Telecommunications (RS-TC) Conduit Design and Installation - Corridor Conduit 1 - 100 mm (4 in.), Trenched

furnish and install conduit

$12.50 $14.14 Topeka, Kansas, United States Actual Linear Foot (LF) 1 WPU1176 "KDOT Unit Costs 2009.pdf" -…
UC2011-01534 Roadside Telecommunications (RS-TC) Conduit Design and Installation - Corridor Conduit 1 - 50 mm (2 in.), Bored

furnish and install conduit

$12.19 $13.79 Topeka, Kansas, United States Actual Linear Foot (LF) 1 WPU1176 "KDOT Unit Costs 2009.pdf" -…
UC2011-01535 Roadside Telecommunications (RS-TC) Conduit Design and Installation - Corridor Conduit 2 - 50 mm (2 in.), Bored

furnish and install conduit

$17.98 $20.34 Topeka, Kansas, United States Actual Linear Foot (LF) 1 WPU1176 "KDOT Unit Costs 2009.pdf" -…
UC2011-01536 Non-ITS Power Cable, 1/C #2

furnish and install power cable

$2.82 $3.36 Topeka, Kansas, United States Actual Linear Foot (LF) 10 General "KDOT Unit Costs 2009.pdf" -…
UC2011-01537 Non-ITS Power Cable, 1/C #8

furnish and install power cable

$1.60 $1.90 Topeka, Kansas, United States Actual Linear Foot (LF) 10 General "KDOT Unit Costs 2009.pdf" -…
UC2011-01538 Non-ITS Bare Ground, 1/C #2

furnish and install bare ground conductor

$2.21 $2.63 Topeka, Kansas, United States Actual Linear Foot (LF) 10 General "KDOT Unit Costs 2009.pdf" -…
UC2011-01539 Non-ITS Bare Ground, 1/C #8

furnish and install bare ground conductor

$1.37 $1.63 Topeka, Kansas, United States Actual Linear Foot (LF) 10 General "KDOT Unit Costs 2009.pdf" -…
UC2011-01540 Roadside Telecommunications (RS-TC) Fiber Optic Cable (12 SMFO)

Furnish single mode fiber optic cable. Does not include installation.…

$2.36 $2.67 Topeka, Kansas, United States Actual Linear Foot (LF) 1 WPU1176 "KDOT Unit Costs 2009.pdf" -…